Correspondence:
10/30/2014 SWPPP Received and Town determined it to be incomplete
11/19/2014 SWPPP Received and Town determined it to be incomplete
12/29/2014 SWPPP Recieved
1/21/2015 SWPPP Accepted
11/20/2015 Phase II SWPPP Review Letter
12/21/2015 Consultant Response Letter Received
1/28/2016 SWPPP Review Letter
2/3/2016 Consultant Response Letter Received
2/22/2016 Revised SWPPP Materials Received
3/2/2016 SWPPP Accepted
3/7/2017 Revised Roof Drain Approval